Face to
Face
Bill Howitt
TAPS Veteran
Published July 2002
On March 1, 1975, Bill Howitt started work as project
engineer in the Pipeline Project Management Group in
Fairbanks. Now a member of the Alyeska Executive Team,
Howitt is one of the dwindling cadre of Alyeska employees
and contractors who have been with TAPS since the start. His
perspectives:
What was it like at the start?
This was brand new stuff. We were young and confident and
thought we could handle any challenge –even though we didn’t
know what the challenges were. I remember on June 22, 1976,
we were pretty euphoric. Then Frank Moolin, the Senior
Project Manager, called the senior construction staff
together. “Gentlemen,” he said. “There is no alternative to
finishing the pipeline by this winter. And today, the days
start getting shorter.” We knocked off the challenges one by
one and by December 1976 the pipeline was done.
What were some of those challenges?
Originally, the Gulkana River pipeline crossing was supposed
to be buried. Late in the game we learned that we couldn’t
bury the pipeline because of permafrost problems. It was too
late to order materials for a new bridge so we to build it
from materials at hand. Another challenge was Thompson Pass.
We had no idea how to manage that 55-degree grade. We
devised the high line system – it was all brand new.
Looking back over 25+ years, what events or achievements
stand out?
First, building throughput to 2 million barrels a day was a
big deal. Pipeline reliability was another. Any system is
very unreliable at first. We kept tackling it until one day
you wake up and realize that we’re at 99 percentplus
reliability. That was a tremendous achievement in just a few
years. Many other crude oil pipelines never exceed 85
percent reliability and that’s considered good. TAPS is
practically off the charts.
The Exxon Valdez oil spill was a huge issue. It changed
public policy but it also changed our focus. It forced us to
look at systems and risk in new ways. We came out of that
with a new willingness to look at ourselves more critically.
We pioneered the use of drag reduction additive (DRA) and
that contributed enormously to maintaining throughput and
efficiency. New designs at Pump Stations 2 and 7, and
careful maintenance scheduling allowed us to sustain high
throughput with substantially less capital investment than
the original design.
What about achievements in recent years?
We took a huge step forward when we developed the ultrasonic
corrosion pig with NKK of Japan. The NKK pig allowed us, for
the first time, to really get ahead of corrosion and tackle
it proactively.
Alyeska just completed a strategic planning effort to chart
the future of the pipeline. We’re looking at some exciting
capital reinvestment plans that would keep the system very
safe, efficient and reliable at lower cost. It’s a
reinvestment in the next 30 years. What’s the lesson you
take from 28 years at TAPS?
The thing I’ve learned over and over is that the guys who
designed this thing were incredibly good. If you’re ever
tempted to mess with the original, you better understand why
they designed it that way. Those guys were really, really
good.