|
|

Pipeline
shutdown for routine maintenance
Work
crews completed two major projects during a scheduled
maintenance shutdown on August 16-17 on opposite sides of the
Trans Alaska Pipeline System (TAPS). The event lasted
approximately 35 hours with over 350 TAPS employees working at
various locations completing nearly 40 additional work tasks.
One of the major projects included installation of roughly 1,700
feet of new 48-inch mainline pipe at Pump Station 2, located
some 60 miles south of Prudhoe Bay. The new piping, pictured at
right, allows the pipeline to completely bypass Pump Station 2
which has not been an active pump station since 1997.
At the terminus of the 800-mile pipeline, crews replaced a 36”
valve at the Valdez Marine Terminal. The replacement valve is on
a piece of equipment called a pig trap receiver, a pipe section
used to receive cleaning and instrument pigs. A pig is a
mechanical device used for routine cleaning or diagnostics on
the pipeline.
“We
planned to complete all of the work within 36 hours and were
able to meet that goal,” said Mike Joynor, SR Vice President
Pipeline and Oil Movements. “Crews work months in advance
outlining the work and credit really goes to all involved for
safely executing the tasks along the pipeline and terminal.”
During the summer’s first shutdown, from June 28-29, Alyeska and
its contractors safely and successfully completed multiple jobs
along the pipeline, including two significant projects. At Pump
Station 9, crews disconnected piping used to operate the
original pumping equipment. Pump Station 9 began operating
newer, upgraded pumps in February 2007. Just outside of
Fairbanks, a team replaced Remote Gate Valve 72 on the mainline
pipe. Remote Gate Valve 72 is one of 177 48-inch mainline valves
along the pipeline.
|
  |