|
|
Forward
Flow achieved at Pump Station 3
This message is from Jim F.
Johnson, Pipeline Vice President, and Mike Joynor, Oil Movements
Vice President.
This week marks the one-year anniversary of the startup of
Electrification & Automation (E&A) equipment at Pump Station 9
(PS 9), which was a significant milestone for E&A and the future
of TAPS. Today, February 12, 2008, with the restart of the E&A
pumps at Pump Station 3, oil is now flowing through new E&A
equipment at two of the planned four E&A pump stations. This
occasion provides a good opportunity to reflect, and take a look
ahead.
When we moved to a phased implementation of E&A at the pump
stations, we decided to first start with PS 9. The facility was
the most accessible of the E&A pump stations, and its proximity
to the commercial power grid meant that we did not have to
install onsite power generation, reducing construction time and
startup complexity. Focusing on PS 9 made sense then, and in
retrospect, it was the right move. During this past year, the
E&A pumps at PS 9 have proved to be highly reliable. The
commercial power provided by GVEA has also been reliable and has
met our requirements.
We learned a great deal from working with the new systems and
pumps at PS 9, and we were able to take lessons learned and
successfully apply them to our subsequent work at Pump Station 3
(PS 3). Similarly, we expect many of these lessons to apply when
E&A work resumes this year at Pump Station 4 (PS 4). This does
not mean our E&A work at any of these sites has been or will be
without bumps. This is a challenging project – the most
significant on TAPS since pipeline construction. But we continue
to deal with and work through challenges as they arise, even if
it means slowing the pace at times. The recent decision to run
PS 3 on legacy pumps while modifications were made to the
Turbine Generators (TGs) is a good example of this. With those
modifications complete, we have restarted the E&A pumps, and we
plan to continue testing and monitoring their performance.
As we move ahead with E&A, finishing work at PS 9 and PS 3,
resuming work at PS 4, and ultimately completing the
implementation of the new system at Pump Station 1, we will
maintain the same high expectations for safety, quality and
performance that were such essential components of our
groundbreaking work at PS 9. Many TAPS employees have
contributed to this effort as it has unfolded – from those
working in documentation, to the project engineers, to the
technicians in the field, and many others along the way. On this
notable anniversary of our efforts, we want to acknowledge the
hard work that has been done.
|
  |