|
Monthly Newsletter Left Menu
|
Face to
Face
Ian Livett
Pump Station Electrification Project Manager
Ian Livett graduated with a civil engineering degree from the
University of
Liverpool in England in 1976 and has spent the majority of his
28-year-career working with BP. He's
been involved in a variety of project engineering and project
management assignments that have spanned the globe, notably the
North Sea (UK & Norway), Middle East,
Gulf of Mexico and Alaska.
Most recently, he was manager of Engineering and Projects for BP's
North Slope operations, including over seeing the development of
satellite fields in the west end of Prudhoe Bay and heavy oil
development at Milne Point. In early
2003 he accepted the position of Pump Station Electrification
Project Manager for Alyeska Pipeline. He is responsible for
design, procurement, construction, commissioning and start-up of
the new electric pump stations.
Q: How will the pump stations change
after reconfiguration?
A: The existing 16,000 horsepower
turbine driven pumps will be replaced with smaller 6,500 hp
electric motor driven pumps controlled by variable frequency
drives (VFD). Existing control rooms will be replaced with new
unmanned control modules and many of the existing utilities will
be removed from service or replaced with modern, more efficient
automated equipment. Pump Stations 1, 3, 4 and 9 are very
standardized. To the greatest extent possible, all the pumps,
motors, variable frequency drives, control systems and control
panels will be identical at each station. This will help reduce
training requirements and the need for equipment spare parts.
Facilities at each station will look very similar and we are
minimizing the number of different vendors providing the
equipment.
Q: What opportunities are
there for Alaska companies?
A: Up to 70 new equipment modules will
be required for the Pipeline Reconfiguration Project. The control
modules, power distribution centers, VFD/switch gear modules,
pump/motor modules, back-up power generation skids and pipe racks
will all be constructed at fabrication shops and transported to
pump stations for installation. Alaska fabricators will be invited
to competitively bid for the fabrication of all the module
packages. Onsite construction at pump stations will include
installation of new modules, foundation piling, pipe racks, power
cables and modifications to existing buildings and infrastructure.
All construction at pump stations will be performed by qualified
Alaska contractor companies. Smaller work packages for work to be
done in existing facilities will be performed by Alyeska's
existing maintenance contractor.
Q: When will module fabrication
begin?
A: Purchase orders (PO's) for two new
power generation modules at Pump Station 5 have already been
awarded to Precision Power in Anchorage. A request for quote (RFQ)
is out for the fabrication of the power distribution center and
control module (two modules) at Pump Station 5. PO's for these
items are anticipated in September. RFQs for the remaining module
fabrication will be released to qualified vendors in
October-November 2004, with awards anticipated 30-40 days later.
Bid packages for on-site construction will be released in December
2004 with awards anticipated in January-February 2005.
|
 |