|
|

Pump Stations
Basic information
Number of stations in original design
12
Number of stations operating as of
June 2004 6: Pump Stations 1, 3, 4, 7and
9;
PS 5 is a relief
station, PS 11 is a security site.
PS 8 was placed in standby June 30, 1996.
PS 10 was placed in standby July 1, 1996.
PS 2 was placed in standby July 1, 1997.
PS 6 was placed in standby August 8, 1997.
PS 12 was placed in standby July of 2002
There were 8 stations operating at
start up (PS 1, 3, 4, 6, 8, 9, 10 and 12). PS 8 pump building was destroyed by an
explosion and fire July 8, 1977, during the start up process; the station was
recommissioned Mar. 7, 1978. PS 2 was commissioned Oct. 2, 1979; PS 7 was commissioned
Dec. 1, 1980.
Number of stations at maximum throughput
11
Crew size
Varies per station, 10-25 Alyeska employees
Crew shifts
1 week on/1 week off, or 2 weeks on/2 weeks
off depending on station; 12 hour work day.
Crude oil holding capacity
- PS 1 420,000 bbl.
- PS 5 150,000 bbl.
- All others 55,000 bbl.
Fire systems, types
Halon, water and foam, dry chemical, wet
chemical, carbon dioxide.
Fire trucks
1 per station
Pump stations associated with airports have
additional designated airfield fire fighting trucks.
Fire Response Team
Pump station personnel.
Fire training
Annual live fire training and monthly fire
response training; airfield rescue fire training provided at stations associated with
airports.
Fire training facilities
Each station has fire extinguisher training
props.
Fuel requirements, per
station, avg. (fuel oil equivalent)
30,000 to 60,000 gallons per day total (see
all operations fuel requirements under Pipeline Operations)
Permanent living quarters, where
provided
At 9 stations: PS 1, 2*, 3, 4, 5, 6*, 7, 10*
and 12. Personnel at PS 8 and 9 live in nearby communities.
* Removed from service when pump
station placed in standby.
Power
Size of power plants ranges from 1.3
megawatts at PS 12 to 4.7 megawatts at PS 6, depending on availability of commercial
power, presence of topping unit and/or vapor recovery system.
Stations generating electrical power
All stations.
Stations also purchasing commercial power
PS 8, 9 and 12.
Pipeline Mileages from/ to Prudhoe Bay/
Fairbanks/ Valdez, and elevations of pump stations
| PS |
Fm.
Prudhoe |
To
Fairbanks* |
To Valdez |
Elevation |
|
| 1 |
0 |
510 |
800.32 |
39 ft. |
| 2 |
57.76 |
444 |
742.56 |
602 ft. |
| 3 |
104.27 |
398 |
696.05 |
1,383 ft. |
| 4 |
144.05 |
356 |
656.27 |
2,763 ft. |
| 5 |
274.82 |
222 |
525.50 |
1,066 ft. |
| 6 |
355 |
139 |
445.32 |
881 ft. |
| 7 |
414.18 |
55 |
386.14 |
904 ft. |
| 8 |
489.28 |
40 |
311.04 |
1,028 ft. |
| 9 |
548.74 |
105 |
251.58 |
1,509 ft. |
| 10 |
585.83 |
145 |
214.49 |
2,392 ft. |
| 11 |
685.99 |
254 |
114.33 |
1,302 ft. |
| 12 |
735.10 |
300 |
65.22 |
1,821 ft. |
| Terminal |
800.32 |
368 |
0 |
142 ft. |
|
|
|
|
|
|
|
|
|
|
* Road miles. PS1-PS7 Dalton & Parks Highways
PS8 - Terminal Glenn & Richardson Highways
|
|
Pumps
Number @ .999 million bbl./day, 2
operating at PS 1, 3 & 9. PS 4, 7 & 12 have 1 unit operating. PS 5 is a relief
station.
Definition
- Full head pump - a two stage pump with both
impellers in series. It has one inlet and one outlet.
- Half head pump - a two stage pump with both
impellers in parallel. It has two inlets and two outlets. It can handle twice the flow of
the full head but only produces half the (head) pressure rise.
Capacity of mainline pumps
- Half head configuration - 60,000 gpm each
- Full head configuration - 20,000 gpm each
Pumps, configuration
- Half head configuration - PS 2 and 7
- Full head configuration - all other pump
stations
- PS 12 is configured to operate wit heither 2
full head or 1 half head pump.
Booster pumps All pump stations have
booster pumps to move oil from the storage tanks to the mainline. (PS 1 has three mainline
booster pumps to boost oil pressure.) PS 5 also has injection pumps
Refrigerated foundations, stations with
5:
PS 1, 2, 3, 5 and 6.
Topping unit, definition
Mini-refinery that produces turbine fuel.
Topping units
All topping units are in standby.
Locations PS 6, 8 and 10.
Topping units at PS 8 and PS 10 in standby in 1996. Topping units
at PS 6 placed in standby in June 1997.
Production capacity
- 2,400 avg. bbl./day of low sulphur turbine
fuel.
Turbines
Fuel requirements
- Gas fired units 4.3 mcf/unit/day avg.
- Liquid fired units
- 30,000 gal./unit/day avg. (half head
configuration)
- 24,000 gal./unit/day avg. (full head
configuration)
Power ratings (sea level, 59° F)
Avon gas generator 24,600 exhaust
gas horsepower.
Reaction turbine
- 18,700 brake horsepower (half head
configuration)
- 15,300 brake horsepower (full head
configuration)
Back to top
|
 |